2014

m/v Wilhelmine & m/v Adeline

Type of work: HFO to MGO conversion
Date: December 2014
Scope of works: 
In anticipation of regulations governing the emissions of the vessel when operating in the North Sea, the vessel was to allow the Main Engine to primarily operate on Marine Gas Oil rather than Heavy Fuel Oil. It was necessary to modify the Main Engine Fuel supply pipe work to accommodate suction from the newly designated Main Engine MGO Service Tank.
The conversion of HFO Settling Tank to a Main Engine MGO Service Tank was also needed.
Installation a new MGO purifier booster pump with a variable speed motor in the Main Engine room.
All necessary series of check valves in the system were delivered and adapted to prefabricated pipe system. Pressure test was performed to ensure the safety, reliability and leak tightness of the new system
 
 
 

Guide frame

Type of work: offshore construction
Date: December 2014
Scope of works: 12 pcs.; total weight: 15,6 tons; in accordance with EN 1090-2 EXC 2

 


Mooring template

Type of work: offshore construction
Date: December 2014
Scope of works: 1 pcs.; total weight: 10,2 tons; in accordance with DNV-OS-C401 , painting NORSOK M-501 system 7B
 
  

     

Ann Rousing

 
Type of work: vessel repair
Date: November 2014
Scope of works:  
- hull washing by high water pressure,
- hull painting including name, registry port and draft marks,
- assembling of new zinc anodes (underwater part of hull, rudder blade, sea chest, bowthruster),
- replacement of anodes in sea chest  (ICAF – System),
- sea valves overhaul
- dismounting of propeller shaft, measuring of the propeller shaft liners clearance , crack test of the cone,      measuring of crankshaft deflection before and after dry – dock, measuring of rudder clearances,
- installation of new fire pump with new foundation and some water pipes,
- dismounting of old protection plates and mounting of new HARDOX 450 plates on bottom of cargo hold,
- replacement of fore bulkhead in tanks top area,
- replacement of the frames in fore wing tanks SB/PS,
- replacement of some parts of the longitudinal bulkheads between the ballast tanks,
- replacement of the shell plates on bulb (app. 2 sqm),
- repairs of leakages between ballast tanks and wing tanks
- making of the small Megger test of main circuits,
- replacement of main switch on auxiliary engine,
- making of small carpentry and upholstery works.
 
  
 

Chem Rotterdam

 
Type of work: bulb renewal
Date: November 2014
Scope of works: prefabrication new bulb section acc to theoretical lines, removing damaged bulb section, fitting new prefabricated, testing, painting, class nk.

   


Basket Frames

Type of work: offshore construction
Date: October - November 2014
Scope of works: 3 units, NORSOK M-101, structural steel fabrication; painting NORSOK M-501 1x2582 kg
 

  


 

Listerland

 
Type of work: vessel repair
Date: October 2014
Scope of works: 
- inspection of the hull, class renewal,
- pipes renewal for fire fighting system,
- pipes renewal for cooling system SG,
- replacement of  deck gantry hydraulic pipes into stainless steel,
- repair of generators sets,
- cleaning and measurements GTR and other electrical panels,
- anchor chain replacement,
- review and certification of lifeboats and davits (SOLAS 1206),
- painting hull underwater part.
 

   


Johan van Veen & Johannis de Rijke

 
Type of work: hopper barges repair
Date: September - October 2014
Scope of works: docking repair, blasting and painting of the hulls, renewal of longitudinal and vertical hopper seals, renewal of half pipes on hopper's coamings, replacement of the coolers together with cooling pipe lines system, renewal of railings stanchions, assembly of 30 tons of steel plates inside the hoppers, renewal of four propellers, replacement of hydraulic cylinder on propellers column, repair of anchor chain, making and assembly of the new exhaust above the main deck replacement of the zinc anodes, repairs works on shell plates under the waterline, repairs manholes to  the dry tanks, the pressure tests of the dry tanks, assembly of roof above the staircase.

   


 

Turret

Type of work: offshore construction
Date: January - October 2014
Scope of works: weight 36 tons, according NORSOK M-101 and M501, flange flatness tolerance +/- 0.2mm. This is top part of Telescopic Pedestal.

 


Telescopic Pedestal

Type of work: offshore construction
Date: January - October 2014
Scope of works: dimensions: 18 x 6,5 x 5,4 m. ,weight 100 tons, according NORSOK M-101 and M501, flange tolerance in range +/- 0.2 mm.

   

 


MSS Workshop Borgland Dolphin

Type of work: offshore construction
Date: June - September 2014
Scope of works: steel construction according to the DNV-GL ; painting according NORSOK M-501 standards with total weight of 28.8 tons, length of 11.5 m, height of 5.19 m and width of 5.9 m.
 
     

Peak Oslo


Type of work: vessel repair
Date: September 2014
Scope of works: steel renewal on the bottom, renewal of the central bulkhead between ballast tanks, supporting of ballast pipes line, repair of air cooler, repair of non return valve in sea chest.
 
    

 

Essencial Enclosure

Type of work: offshore construction
Date: April - August 2014
Scope of works: steel construction according to the NORSOK M101 ; painting according NORSOK M501 standards with total weight of 43 tons, length of 12,9 m, height of 6,4 m and width of 6,9 m.
 
 
         

 

Open Top Container

Type of work: offshore construction
Date: July - August 2014
Scope of works: steel constructions according to the DNV 2.7.3.
 

  

 


Guiding system to windfarm

Type of work: offshore construction
Date: June - July 2014
Scope of works: 18 pcs.; total weight: 25 tons, in accordance with DNV-GL 2.7.1 standards.
 


 

Seafastening frames

Type of work: offshore construction
Date: March - April 2014
Scope of works: 2 pcs.; total weight: 63 tons, in accordance with DNV-GL 2.7.1 standards.
 

       
 

Listerhav

Type of work: vessel repair
Date: March - April 2014
Scope of works: spot grit blasting, underwater part painting, sea chests cleaning, ballast tanks tank top renewals,  gangways repairs.
 
 v
,

Smorbukk Plet fabrication

Type of work: offshore subsea structures and spreader bars
Date: January - June 2014
Scope of works: fabrication of subsea structures:
  • PLET Stand alone – 2 pieces, 17 tones each,
  • PLET Integrated – 2 pieces, 12 tones each,
  • Spreader bar – 2 pieces, 23 tones each.
  

ROV Hangar

Type of work: offshore construction
Date: November 2013 - March 2014
Scope of works: 135 tons of steel, according by NORSOK M-501 and DNV standards, equipped.
 
   

20ft Gexsys Containers

Type of work: offshore construction
Date: November 2013 - February 2014
Scope of works: steel constructions according to the NORSOK M101 and DNV 2.7.1 standards
 
  
 